Agrium plant to be offline for eight weeks

Agrium Inc.’s Carseland, Alberta, nitrogen plant is expected to be down for about eight weeks for repairs. It was down earlier this year for two-three weeks.

The complex went down Feb. 20 due to a problem with a high pressure heat exchanger in the urea unit. While this would have taken only about three weeks to repair, Agrium is opting to move forward a planned six week Carseland turnaround for July-August to coincide with the current outage. As a result, the facility may be down for up to eight weeks.