US Gulf:
Harvey
Lock travel has remained unavailable since Oct. 2 due to low water conditions
on the lower Mississippi River. A guidewall replacement project underway since
Aug. 1 at Bayou Sorrel Lock blocked Monday-through-Friday travel intermittently
between 6:30 a.m. and 5:00 p.m., with 24-hour movements resuming on Saturdays
and Sundays. Work at the site was scheduled to continue into March 2023.
Due to the presence of exposed underwater pipelines,
traffic was completely halted through the Atchafalaya River’s Little Island
Pass, Middle Island Pass, and Riverside Pass during the week. Detours were
available through the Port Allen Route.
Restrictions on tow lengths and widths remained in
place on unassisted lockages at Algiers
Lock, sources said, limiting vessels traveling without industry assistance to
four standard barges or two 30,000 mt tankers per turn. Larger lockages were
possible with the use of an assist tug. Corps data showed wait times at 26
hours on Nov. 7.
Dredging
in the New Orleans Harbor was scheduled to wrap up on Nov. 7. Port Allen Lock
delays were reported up to 40 hours during the week, while boats transiting
Industrial Lock saw 9-12 hour wait times on Nov. 6-7. Intermittent Colorado
Lock waits were noted in the 6-12 hour range.
Mississippi River:
Historic low water levels on the lower Mississippi
River continued during the week, limiting the industry’s ability to move products
on the Eastern River System.
Draft limits for solid cargoes have remained at 9.0
feet since Oct. 17 in both the northbound and southbound directions on the full
length of the waterway, a 25-30% reduction from normal limits, while liquid
cargoes were capped at 8.5 feet of draft. Localized draft limits were heard as
low as 7.0 feet for loading and unloading.
Tows were reduced to a maximum 25 barges on
southbound travel, below the typical 30-40 cargo limit, depending on region.
Combined with draft limitations, carrying capacity on some tows was reduced by
more than 50% from normal levels, sources said.
Oceangoing vessel drafts were reduced to 41 feet
from 45 feet at the Port of Baton Rouge, La.
River levels at Vicksburg, Miss., rose to 4.19 feet
on Nov. 9, although depths remained below the five-foot Low Stage threshold. The
Memphis, Tenn., gauge stood at (-)8.5 feet, also below that area’s five-foot
Low Stage, while the St. Louis gauge climbed to 2.35 feet from the week-ago
(-)0.45 feet. St. Louis was expected to fall below 0.0 feet on Nov. 16, while
Vicksburg and Memphis were both projected to hold at Low Stage through Nov. 22.
Dredging started on Nov. 6 at Stack Island, located
at Miles 485-486, and was expected to run through approximately Nov. 14, closing
the area up to 48 hours at a time.
Revetment work at Mile 344 prompted daily travel
shutdowns between 6:00 a.m. and 6:00 p.m., and is expected to run through Nov.
17. The project was slated to relocate to Mile 336 on Nov. 17-25. A safety
advisory is in place at Miles 228-230 due to repairs in progress at the I-10
bridge. Pipeline removal at Mile 189 was scheduled conclude on Nov. 8.
Dredging at the upper river’s Mile 184 closed the
area to overnight travel, prompting delays up to 23 hours at Chain of Rocks
Lock. Work was slated to run through approximately Nov. 14. Wait times at Lock
22 were reported up to 10.5 hours.
Illinois River:
Sources noted raised wickets at Peoria Lock and LaGrange Lock again during the week
due to low water levels, forcing lockages through both locations. Wait times
were noted at 3-7 hours at LaGrange Lock. Travel through Dresden Island Lock
saw delays in the 4-11 hour range.
Ohio River:
Low water conditions continued on the Ohio River, resulting
in nine-foot draft restrictions on the river’s full length. Nine-foot draft
limits were reported in effect for the Tennessee and Cumberland Rivers as well.
Dredging in progress at Miles 965-974 forced
staggered one-way travel restrictions through the Mound City, Mo., area,
sources said.
Replacement of the main chamber miter gate at
Cannelton Lock was expected to conclude on Nov. 11. The project has forced all
navigation through the auxiliary chamber, triggering delays in a wide 26-54
hour range during the week.
The main chamber at Montgomery Lock is shut through
Dec. 16 for repairs and maintenance. Tows detouring through the secondary
chamber reportedly faced 2-4 day waits during the week, up from 2-3 days in the
prior report. Belleville Lock waits were noted up to 24 hours.
Arkansas River:
Norrell Lock remains closed to daytime navigation
through Nov. 20, blocking travel daily from 7:00 a.m. to 7:00 p.m., while
overnight lockages were limited to 70-foot widths. The lock is scheduled to
shut completely to navigation on Jan. 30-31, 2023.